1. What is the difference between crashing and fast-tracking? 2. What is a

Can’t do an assignment? Get it done by a trustworthy essay writing service

Order A custom Order

1. What is the difference between crashing and fast-tracking?
<
2. What is a project buffer in “Critical Chain Method (CCM)”? How is CCM different from CPM?
<
3. How is GERT different from PERT? What are its benefits and drawbacks?
<
4. The estimated installation cost rate to install 100 computers in a data center is $10 per computer. The total duration of the project is planned to be 8 weeks. At the end of 3 months after the project is started, the project team noted that 30 of the 100 computers had been installed, incurring a cost of $36,282. Using your knowledge of EVM and confidence intervals, forecast the project’s final schedule and cost at the current performance rate.

Can’t do an assignment? Get it done by a trustworthy essay writing service

Order A custom Order

Published
Categorized as English

Leave a comment